Steps in Building a Custom Home
Prepare and agree on budget
Get permit to build (if inside city limits)
Build pad
Build foundation
- Foundation men lay out foundation
- Plumber runs drain lines
- Foundation men finish framing foundation and dig trenches
- Plumber runs copper (this finishes rough out and he takes first of three draws)
- Foundation men run steel
- Electrician sets floor plugs
- HVAC runs vents if necessary
- Treat for termites
- Pour foundation
Framing begins
- Order windows
- Order special plumbing fixtures
- Order front door, back doors
- Pick roof shingles
- Pick brick
- Order cabinets
- Put felt on after decking
- Put windows in
- Put in doors and construction locks
- Finish framing, order inspection
Top Out
- Order interior doors
- Electrician runs wiring
- Plumber sets tubs, raises copper
- HVAC run ducts
- Pest control system installed
- Sound and security wiring
- Brick anytime in next month
Pick style of trim (crown mold, baseboard, interior doors)
Insulation
- Sheetrock
- Order tile
- Order carpet
- Order counter tops
- Pick light fixtures
- Pick lock out package (door knobs, toilet fixtures, etc.)
Tape/float/texture
Trim starts
- Install cabinets
- Install interior doors
- Trim baseboards, crown molding, chair rail, etc.
- Paint
- Tile
Trim Out
HVAC final
- Set vanity tops
- Trim out plumbing
- Final concrete driveway, sidewalks
Install Carpet
Lock Out
- Door knobs, towel, toilet fixtures, door stops, closet rods
- Hang doors
Order final inspections
- Order gas installed
- Electrical, call WTU for permanent hook up after inspection by city
- Plumbing
- Mechanical
- Total final
Touch up punch list
Close